Costing:Concept of equivalent units.

System
System Posts: 100,534 🤖 Admin 🤖
edited June 18 in AAT student discussion
Can anyone tell me the answer to this i did it in class this week n a cannot remember how i arrive at the total cost, it doesnt make any sense!

In a given period production and cost data were as follows

materials: £5115
labour: £3953
Overheads: £3000
12067

Production was 1400 fully complete units and 200 partly complete units the degree of completion was as follows:

mat: 75%
lab: 60%
o/h:50%

so an extract of my answer to this i have:

cost element equiv in wip fully completed units

materials 200x75%=150 1400

total cost cost per unit
545 3.30

How is the 545 worked out?

cheers

Comments

  • System
    System Posts: 100,534 🤖 Admin 🤖
    Re:Costing:Concept of equivalent units.

    I'm not entirely sure what you mean by 'total costs' in this context so it's hard to say.

    Just working through the materials bit:

    Total eq units = 1400 + 150 = 1550
    Cost/unit = 5115/1550 = 3.3
    Value of WIP = 3.3 x 150 = 495

    Working through the other costs I didn't have 545 coming up anywhere. I guess that's not much help but was a useful bit of revision for me anyway!

    Chris
Privacy Policy