splitting down variances - PEV
System
Posts: 100,534 🤖 Admin 🤖
Hi All
It is me again begging for help.
I keep having real problems when the question asks to split down a certain variance (usually material price or labour efficiency) into the change relating to a drop/increase or training and then other reasons.
Is there a logical way of doing this, because I know that the resulting 2 variances must equal the original one, but I cannot figure out which figures to use to start with.
Any help would be great.
Many thanks again
Eva :roll:
It is me again begging for help.
I keep having real problems when the question asks to split down a certain variance (usually material price or labour efficiency) into the change relating to a drop/increase or training and then other reasons.
Is there a logical way of doing this, because I know that the resulting 2 variances must equal the original one, but I cannot figure out which figures to use to start with.
Any help would be great.
Many thanks again
Eva :roll:
0
Comments
-
Re:splitting down variances - PEV
I think you have to compare like with like, so adjust the original standard price to the new inflation adjusted price.
the original variance was
actual quantity x (std price-actual price)
split this formula into two. The first item must be first in the inflation adjusted formula, and the last item must be the last item in the 'other reasons' formula, so your inflation adjusted price goes in the middle
inflation= actual quantity x (std price - inflation adjusted price)
other reasons = actual quantity x (inflation adjusted price - actual price)
I'm so sad I actually colour co-ordinate all my variances - my exam sheet is going to look like a rainbow!
0 -
Re:splitting down variances - PEV
Hi Jackie
That is brilliant - I will give it a go.
Many thanks
Eva
0 -
Re:splitting down variances - PEV
To calculate your inflaction price you will be give some kind of index number or additional information
i.e:- (based on additional information)
Labour Efficiency subdivision
actual hours were 36,800 for 20,000 units of output costing 184,000, standard hourly output was 2hrs @ £4.85.
Once trained efficiency will be improved by 15%.
Calculations:
Labour Efficiency Variance = £15,520 (F)
(40,000(2x20,000)-36,800)) x 4.85 = 5520
Variance due to untrained workers = £26,772 (A)
36,800hrs x 15% = 5,520hrs
36,800hrs - 5,520hrs = 31,280hrs
(36,800hrs - 31,280hrs) x 4.85 = 26772
Variance due to other reasons = £42,292 (F)
Regards
Dean
p.s if you have time and want to prove the variance due to other reason you can do so like this:-
budgeted hours = 40,000hrs
revised standard = 31,280hrs
(31,280 - 40,000) x £4.85 = 42292F
0 -
Re:splitting down variances - PEV
i.e:- (based on index numbers)
Material Price subdivision
actual litres used were 36,000 @ £1.20 per litre the standard being £1.50
The standard was based on a price indexation of 15 but when the actual production took place it was 20.
Calcualtions:
Material Price Variance = £10,800 (F)
(1.50-1.20) x 36,000 = 10800
Variance due to indexation = £3,600 (A)
1.20 x (20/15) = 1.60
1.50 - 1.60 = 0.10
0.10 x 36,000 = 3600
Variance due to other reasons = £14,400 (F)
Regards
Dean
p.s if you have time and want to prove the variance due to other reason you can do so like this:-
actual price 1.20
revised standard 1.60
(1.60-1.20) x 36,000 = 14400(F)0 -
Re:splitting down variances - PEV
Many thanks Dean, that is really useful aswell.
Eva
0 -
Re:splitting down variances - PEV
I've just made that up so it would be good if Sandy could check that to make sure its right
but your more than welcome!
Regards
Dean0