ECR June 2005 Task 2.4
podolibrno
Registered Posts: 1 New contributor 🐸
could anyone please answer my questions on ECR June 2005 Task 2.4
how can i rank products B and C and how to work out *machine hours allocated to B and C*
thank you very much for your help.
how can i rank products B and C and how to work out *machine hours allocated to B and C*
thank you very much for your help.
0
Comments
-
You rank the product that gives the greater contribution first, which in this question is product B.
Therefore, priority is given to this for machine hours - a previous question gives the information that 1,000,000 machine hours are required to produce the full budgeted amount.
Product C requires 3,750,000 hours for full production, but as the total machine hours are limited to 3,500,000 you can only allocate 2,500,000 (3,500,000 less 1,000,000 used for 'B') hours to producing C.0
Categories
- All Categories
- 1.2K Books to buy and sell
- 2.3K General discussion
- 12.5K For AAT students
- 318 NEW! Qualifications 2022
- 161 General Qualifications 2022 discussion
- 11 AAT Level 2 Certificate in Accounting
- 56 AAT Level 3 Diploma in Accounting
- 87 AAT Level 4 Diploma in Professional Accounting
- 8.8K For accounting professionals
- 23 coronavirus (Covid-19)
- 272 VAT
- 92 Software
- 273 Tax
- 135 Bookkeeping
- 7.2K General accounting discussion
- 200 AAT member discussion
- 3.8K For everyone
- 38 AAT news and announcements
- 345 Feedback for AAT
- 2.8K Chat and off-topic discussion
- 582 Job postings
- 16 Who can benefit from AAT?
- 36 Where can AAT take me?
- 42 Getting started with AAT
- 26 Finding an AAT training provider
- 48 Distance learning and other ways to study AAT
- 25 Apprenticeships
- 66 AAT membership