PCR December 2008 Task 2.2

shama72
shama72 Registered Posts: 8 New contributor 🐸
Hi everyone
Could anyone help me with this question pls,

Task 2.2 Labour overtime also Rent and Rates, i managed to get a different answer to the examiners one, could any one show me how he managed to get note 1 and note 2 to acheive the labour overtime figure of: 819,000 and also the figure for rent: 300,000.

thank you

Comments

  • SandyHood
    SandyHood Registered, Moderator Posts: 2,034 mod
    Task 2.2 Labour overtime also Rent and Rates, i managed to get a different answer to the examiners one, could any one show me how he managed to get note 1 and note 2 to acheive the labour overtime figure of: 819,000 and also the figure for rent: 300,000.
    1. Labour overtime - I got £819,000 (240,000 chargeable hours less the basic 175,000 gives the overtime hours. Then multiply by £12.60 per hour)
    2. Rent I got £300,000. It is a stepped cost with £75,000 per step and 4 steps
    Sandy