Standard costing variances
Primble
Registered Posts: 734 Epic contributor 🐘
Hi,
I am useless at this. what are all the formulas i need to remember for variances?
is standard the same as budgeted amounts?
I am useless at this. what are all the formulas i need to remember for variances?
is standard the same as budgeted amounts?
0
Comments
-
I'm struggling with exactly the same thing - I've spent all day teaching myself from the text books but when I look at past papers they calculate things differently and get different answers
Standard is the different between actual and budgeted0 -
Variances
Hi both. As far as I understand it, there are actually 3 things:
1) Budgeted costs.
This is the original plan as it were. From this you can calculate the 'standard cost' of one item, e.g. budgeted £2,000 to make 100 units then the standard cost of 1 unit is £2,000 / 100 units = £20 per unit.
2) Actual costs
Say £2,500. Note that you may actually have made more than you budgeted, e.g. made 120 units.
You cannot simply say you spent £500 more than budget because you are comparing a budget for 100 units with actual costs for 120 units. So you need to calculate a 'flexed' budget (or revised budget if you like) for the 120 units so you can compare like with like. So:
3) Flexed / revised budget
As simple as saying £20 per unit x actual 120 units made = new budget of £2,400 (which is £400 more than the original budget).
So now you have:
* 120 units: budget £2,400
* 120 units: actual costs £2,500
The total variance is £100 and you need to look at the individual variances causing this. I won't go through all the formulae here, but I've found the formulae used can be varied - a lot of it is shortcuts for people who know exactly what they are doing. If you aren't confident with this - or liable to forget under exam pressure like me - then I suggest you go the more long-winded but reliable method which can be worked out through first principles:
E.g. Calculate the material price variance when you are told:
Budget is £120,000 for 10,000 kg
Actual is £147,000 for 10,500kg.
Standard price per kg (from the budget) = £120,000 / 10,000kg = £12 per kg
So the actual 10,500kg should have cost £12/kg x 10,500kg = £126,000 (this is the flexed budget for actual material used)
But it actually cost £147,000
So the material price variance is £147,000 actual - £126,000 expected = £21,000 ADVERSE (it cost more than expected).
You can double-check if you like: Actual £147,000 / 10,500kg = £14 per kg.
Another way is to say it should have cost £12 per kg but actually cost £14 per kg. Paid an extra £2 per kg, x actual 10,500kg = £21,000 extra paid.
The other variances are similar - calculate what it should have cost for the actual units, then what it actually cost for the actual units, then the variance is the difference.
Hope this helps - and good luck!0 -
thanx suju. really great post. atlast the mystery of standard and budegeted has been solved!!!. thank u0
-
is standard the same as budgeted amounts?
My confusion is with the terminology certain amounts are called in the text books or past papers, examples:
*the original Budget sometimes is called Standard
*the Flexed budget is also called Standard
Therefore when the question ask to "calculate the standard cost of something" sometimes I don't know if it refers to the budget amount or the flexed one!:confused1:0 -
this is why i get confused0
-
I'll take your comment and expand a little as abbreviations can lead to confusion:*the original Budget sometimes is called Standard
*the Flexed budget is also called Standard- The original budget is the standard cost of one unit multiplied by the budgeted number of units
- The flexed budget is the standard cost of one unit multiplied by the actual number of units
Sandy
sandy@sandyhood.com
www.sandyhood.com0
Categories
- All Categories
- 1.2K Books to buy and sell
- 2.3K General discussion
- 12.5K For AAT students
- 322 NEW! Qualifications 2022
- 159 General Qualifications 2022 discussion
- 11 AAT Level 2 Certificate in Accounting
- 56 AAT Level 3 Diploma in Accounting
- 93 AAT Level 4 Diploma in Professional Accounting
- 8.8K For accounting professionals
- 23 coronavirus (Covid-19)
- 273 VAT
- 92 Software
- 274 Tax
- 138 Bookkeeping
- 7.2K General accounting discussion
- 201 AAT member discussion
- 3.8K For everyone
- 38 AAT news and announcements
- 345 Feedback for AAT
- 2.8K Chat and off-topic discussion
- 582 Job postings
- 16 Who can benefit from AAT?
- 36 Where can AAT take me?
- 42 Getting started with AAT
- 26 Finding an AAT training provider
- 48 Distance learning and other ways to study AAT
- 25 Apprenticeships
- 66 AAT membership