Dec08 PCR Paper

debbieh
debbieh Registered Posts: 17 New contributor 🐸
Help please Section 1 (e) hours required number of units is 550,000 takes 12 minutes of labour time to assemble, so I thought you would 550,000 * 12, but the answer is 110,000 hours, confused, please could some one help.

Thanks

Comments

  • A-Vic
    A-Vic Registered Posts: 6,970 Beyond epic contributor 🧙‍♂️
    debbieh wrote: »
    Help please Section 1 (e) hours required number of units is 550,000 takes 12 minutes of labour time to assemble, so I thought you would 550,000 * 12, but the answer is 110,000 hours, confused, please could some one help.

    Thanks

    well wouldnt it be 12 mins so (60/12) 5 in an hour so 550,000/5 = 110,000 hours

    I think you just have to work out how many you can produce in one hour then divide it by the units
  • debbieh
    debbieh Registered Posts: 17 New contributor 🐸
    pcr dec2008

    Thanks
  • slim shady
    slim shady Registered Posts: 1 New contributor 🐸
    Hi i did this one last week
    Its the products needed * the mins per unit / 60 to get bthe hours needed hope this helps