Hi,

I am trying to resolve question 5.1 Chapter Activities Osborne books and Task 2.1 from practice Assessment April 2010, i am stuck on how to calculate Equipment hire.

Can anybody help me please?

Thank you

Comments

  • PGM
    PGM Registered Posts: 1,954 Beyond epic contributor 🧙‍♂️
    If you can type the question in?
  • rehana
    rehana Registered Posts: 61 Regular contributor ⭐
    If it is the one where you have to flex it to 75000
    Then the budgeted cost for 80 000 units is £15000 and the notes tell you that equipment hire is based on a cost for each 8000 units or fewer.

    80 000/8000 = 10
    £15000/10 = £1500 per 8000 units

    for 75000 units

    75000/8000 = 9.375 so will still be 10

    10 x £1500 = £15000