Budgeting question, steped cost
ms sadat
Registered Posts: 39 Regular contributor ⭐
in monthly operating statment.
budget unit volume is 76000.
Actual unit volume is 80000.
Flexed budget volume is 80000.
Equipment hire budget cost is £48000.
Equipment hire actual cost is £50000.
The budget for equipment hire is Steped ,increasing at every 15000 units of monthly production.
I have the answer for equipment flexed budget which is £48000 , but i dont know how becos we got another question where
budget units volume is 76000.
actual units volume is 72000.
flexed budget units volume is 72000.
equipment hire cost budget is £48000.
equipment hire cost actual is £42000.
and again The budget for equipment hire is Steped ,increasing at every 15000 units of monthly production.
i have the answer for flexed budget for equipment which is £ 40000.
i am kind of confused
anybody who can help .appreciated.
budget unit volume is 76000.
Actual unit volume is 80000.
Flexed budget volume is 80000.
Equipment hire budget cost is £48000.
Equipment hire actual cost is £50000.
The budget for equipment hire is Steped ,increasing at every 15000 units of monthly production.
I have the answer for equipment flexed budget which is £48000 , but i dont know how becos we got another question where
budget units volume is 76000.
actual units volume is 72000.
flexed budget units volume is 72000.
equipment hire cost budget is £48000.
equipment hire cost actual is £42000.
and again The budget for equipment hire is Steped ,increasing at every 15000 units of monthly production.
i have the answer for flexed budget for equipment which is £ 40000.
i am kind of confused
anybody who can help .appreciated.
0
Comments
-
in monthly operating statment.
budget unit volume is 76000.
Actual unit volume is 80000.
Flexed budget volume is 80000.
Equipment hire budget cost is £48000.
Equipment hire actual cost is £50000.
The budget for equipment hire is Steped ,increasing at every 15000 units of monthly production.
First you need to work out the cost per stepped cost. 76000/15000 = 5.066 so 6 steps are needed.
£48000 / 6 steps = £8000 per step
For the flexed budget you do: 80000/15000 = 5.333 so 6 steps again, so the flexed amount is the same as previously (£48000)budget units volume is 76000.
actual units volume is 72000.
flexed budget units volume is 72000.
equipment hire cost budget is £48000.
equipment hire cost actual is £42000.
and again The budget for equipment hire is Steped ,increasing at every 15000 units of monthly production.
i have the answer for flexed budget for equipment which is £ 40000.
i am kind of confused
anybody who can help .appreciated.
As the original figures for working out the cost per step is the same we just do the second part.
72000/15000 = 4.8 so 5 steps are needed
5 steps * £8000 = £40000
Hope that helps0 -
Thx Wooof...!
Appreciated . totally got it now ..0
Categories
- All Categories
- 1.2K Books to buy and sell
- 2.3K General discussion
- 12.5K For AAT students
- 328 NEW! Qualifications 2022
- 161 General Qualifications 2022 discussion
- 11 AAT Level 2 Certificate in Accounting
- 57 AAT Level 3 Diploma in Accounting
- 95 AAT Level 4 Diploma in Professional Accounting
- 8.9K For accounting professionals
- 23 coronavirus (Covid-19)
- 273 VAT
- 92 Software
- 275 Tax
- 138 Bookkeeping
- 7.2K General accounting discussion
- 203 AAT member discussion
- 3.8K For everyone
- 38 AAT news and announcements
- 345 Feedback for AAT
- 2.8K Chat and off-topic discussion
- 584 Job postings
- 16 Who can benefit from AAT?
- 36 Where can AAT take me?
- 42 Getting started with AAT
- 26 Finding an AAT training provider
- 48 Distance learning and other ways to study AAT
- 25 Apprenticeships
- 66 AAT membership