HELP Financial Performance

Jade95
Jade95 Registered Posts: 50 Epic contributor 🐘
My result for financial performance was NYC, so here we go again second time round on Wednesday. Now looking through practice papers and found some thinngs that i am not sure how the AAT worked out, any help would be appreciated. :001_smile:

CBT - 1

1.4

I can't seem to reach the answer for Direct materials bottles usage.

The AAT have - £60, i got - £260.

This is how i got my answer...

Usage variance = SP(SQ - AQ)

Sp = £2000/10000 = 0.2

SQ = 10000 AQ = 11300

So...

0.2 x (10000 - 11300)
0.2 x (-1300)
= -260

Any Ideas!

I also don't see where the figure for the budgeted standard cost for actual production.

The AAT got 30030, i'm not sure how they got to this answer.

Any ideas!

Thanks in advance.

Comments

  • Clintm15
    Clintm15 Registered Posts: 248 Dedicated contributor 🦉
    Hi Jade,

    It's calculated like this...

    The standard quantity is 10,000 units / 10,000 bottles = 1 unit per bottle.

    The standard quantity of actual production = 1 unit per bottle * 11,000 actual bottles = 11,000 units.

    The standard price = £2,000 budgeted material cost / 10,000 standard units = £0.20

    So the standard quantity of material for actual production at standard price = 11,000 * £0.20 = £2,200

    The actual quantity of material at standard price = 11,300 * £0.20 = £2,260


    So..

    £2,200 - £2,260 = -£60 or £60 Adverse

    I hope this clears things up for you :)
    AAT
    Level 2 - 2011
    Level 3 - 2012
    Level 4 - 2013

    ACCA
    F4 - Corporate Law - Dec 2015 (passed)
    F5 - Performance Management - Dec 2014 (passed)
    F6 - Taxation - Dec 2013 (passed)
    F7 - Financial Reporting - Jun 2014 (passed)
    F8 - Audit & Assurance - Dec 2015 (passed)
    F9 - Financial Management - Jun 2015 (passed)
  • Jade95
    Jade95 Registered Posts: 50 Epic contributor 🐘
    Thank you Clintm 12

    That has cleared it up, i did get £2260 at one point but wasnt sure.

    Also do you know how they got the £30030 for the budgeted standard cost for actual production, because i normally work out the variances and work backwards.

    Thanks again :)
  • Clintm15
    Clintm15 Registered Posts: 248 Dedicated contributor 🦉
    No problem Jade.

    Budgeted/Standard cost of actual production is calculated like this.....

    Total budgeted cost = £27,300

    Budgeted production = 10,000 bottles

    Budgeted cost of production per bottle = £27,300 / 10,000 = £2.73

    Actual production = 11,000 bottles

    Budgeted cost of actual production = 11,000 * £2.73 = £30,030


    That's the long version for clarity, it could have been calculated like this...

    11,000 / 10,000 = 1.1
    1.1 * £27,300 = £30,030

    :)
    AAT
    Level 2 - 2011
    Level 3 - 2012
    Level 4 - 2013

    ACCA
    F4 - Corporate Law - Dec 2015 (passed)
    F5 - Performance Management - Dec 2014 (passed)
    F6 - Taxation - Dec 2013 (passed)
    F7 - Financial Reporting - Jun 2014 (passed)
    F8 - Audit & Assurance - Dec 2015 (passed)
    F9 - Financial Management - Jun 2015 (passed)
  • Jade95
    Jade95 Registered Posts: 50 Epic contributor 🐘
    Thanks once again, very clear now. :laugh:

    I wish the AAT would show how they got their answers to the practice assessments, assesments would be much easier :lol:

    Thank you

    Jade:001_smile:
  • Days Days
    Days Days Registered Posts: 6 Regular contributor ⭐
    u r great man
Privacy Policy