Help Budgeting..... 1.2 (D)

sgafo
sgafo Registered Posts: 21 Dedicated contributor 🦉

Can someone help me please

budgeting question 1.2 (D)



attachment.php?attachmentid=399&d=1367090084

Comments

  • Nps
    Nps Registered Posts: 782
    In the time available, only 7000 units can be produced ((350 hours x 60 minutes)/3 minutes)

    This leaves 410 which will need to be subcontracted.
  • Jo Clark
    Jo Clark Registered Posts: 2,525 Beyond epic contributor 🧙‍♂️
    sgafo wrote:
    Can someone help me please

    Hello sgafo

    When are you due to sit your budgeting exam? NPS has kindly provided you with the answers and workings to at least 4 questions, however I would be slightly concerned if you are struggling to answer this many questions having completed the relevant studying.

    Please don't take offence at this message, however there have been several posts in the past that discuss how students simply learn by rote and use the practice exams to 'learn from' expecting the actual exams to be the same. I would strongly advise against this.

    I wish you well with your exam.


    JC
    ~ An investment in knowledge always pays the best interest ~
    Benjamin Franklin
  • Nps
    Nps Registered Posts: 782
    I admit I thought the same as Jo.

    To be honest I wasn't sure which bits you were struggling with as some of the questions were very basic and just required some simple adding up. Hopefully it is just a case of you getting bogged down with the technical side of things and looking for complications that aren't there in the easier questions.