Budgeting AAT AQ2013 sample assessment 2 Task 6 (b)

Canuck74Canuck74 Just JoinedPosts: 8Registered
I can't figure out how the Material price and Material usage was calculated.

I was able to calculate the Standard raw material cost of production 94500/63000= 1.50 1.50*65000= 97,500

Activity data Items produced Kg used Cost

Budget 63,000 31,500 94,500

Actual results 65,000 33,500 99,000


The answer for the Material price variance: 1,500 and for the Material usage variance is -3,000