Can someone please help me with practice assesment 1 task 3 b please thank you

Can someone please help me with practice assesment 1 task 3 b please thank you

Comments

  • Kkadijat
    Kkadijat Registered Posts: 28
    The budgeted cost is £350000 and the variance is £35000Favourable, this means LESS money has been spent than budgeted hence £350000-£35000=£315000 ACTUAL COST