Original budget is 121000 units actual 105000 units
Energy 80000 actual 78000
Energy cost is semi variable the variable element is 0.50 per unit how do you work out the semi variable cost please
Energy 80000 actual 78000
Energy cost is semi variable the variable element is 0.50 per unit how do you work out the semi variable cost please
0
Comments
-
Step 1
Find the fixed cost
We already know that the total budgeted energy cost is. £80,000
The variable element is 121,000 units x £0.50/unit =...... £60,500
The difference between the two is the fixed cost..............£19,500
Step 2
Using the actual units find the total (flexed) energy cost
The fixed cost is ............................................................£19,500
The variable element is 105,000 units x £0.50/unit........£52,500
Total Energy cost (semi-variable cost)...........................£72,000Sandy
sandy@sandyhood.com
www.sandyhood.com5 -
Thank you for your help0
Categories
- All Categories
- 1.2K Books to buy and sell
- 2.3K General discussion
- 12.5K For AAT students
- 322 NEW! Qualifications 2022
- 159 General Qualifications 2022 discussion
- 11 AAT Level 2 Certificate in Accounting
- 56 AAT Level 3 Diploma in Accounting
- 93 AAT Level 4 Diploma in Professional Accounting
- 8.8K For accounting professionals
- 23 coronavirus (Covid-19)
- 273 VAT
- 92 Software
- 274 Tax
- 138 Bookkeeping
- 7.2K General accounting discussion
- 201 AAT member discussion
- 3.8K For everyone
- 38 AAT news and announcements
- 345 Feedback for AAT
- 2.8K Chat and off-topic discussion
- 582 Job postings
- 16 Who can benefit from AAT?
- 36 Where can AAT take me?
- 42 Getting started with AAT
- 26 Finding an AAT training provider
- 48 Distance learning and other ways to study AAT
- 25 Apprenticeships
- 66 AAT membership