Registered Posts: 16 New contributor 🐸
Hi I am 2 weeks away from my exam budget and I going through question after question and one question I am stuck with
5630 units product are to be manufactured next week
Each unit takes 2.5 minutes produce
200 production labour hours are available
Any additional requirement must be sub-contracted
How do you work this out please
Thanks linda
5630 units product are to be manufactured next week
Each unit takes 2.5 minutes produce
200 production labour hours are available
Any additional requirement must be sub-contracted
How do you work this out please
Thanks linda
0
Comments
-
Linda
200 production labour hours are available
each unit takes 2.5 minutes produce
So we can make 24 units per hour. [60 minutes in an hour/2.5 minutes per unit]
and 4800 units in 200 hours
But we need 5630 units which is 830 more than we can make
So must sub-contract the production of 830 units.
I hope that helpsSandy
sandy@sandyhood.com
www.sandyhood.com0 -
Hi thanks it as just answering as many question as I can ready for the exam0
Categories
- All Categories
- 1.2K Books to buy and sell
- 2.3K General discussion
- 12.5K For AAT students
- 328 NEW! Qualifications 2022
- 161 General Qualifications 2022 discussion
- 11 AAT Level 2 Certificate in Accounting
- 57 AAT Level 3 Diploma in Accounting
- 95 AAT Level 4 Diploma in Professional Accounting
- 8.9K For accounting professionals
- 23 coronavirus (Covid-19)
- 273 VAT
- 92 Software
- 275 Tax
- 138 Bookkeeping
- 7.2K General accounting discussion
- 203 AAT member discussion
- 3.8K For everyone
- 38 AAT news and announcements
- 345 Feedback for AAT
- 2.8K Chat and off-topic discussion
- 584 Job postings
- 16 Who can benefit from AAT?
- 36 Where can AAT take me?
- 42 Getting started with AAT
- 26 Finding an AAT training provider
- 48 Distance learning and other ways to study AAT
- 25 Apprenticeships
- 66 AAT membership