Assessment 2 Task 1.3

Options
sophie_612
sophie_612 Registered Posts: 136 Dedicated contributor 🦉
Hi,

Can someone tell me how i would know the answer to the highlighted parts the rest i know just confused on those couple of things.

Thanks
Sophie



Comments

  • CornishPixie
    CornishPixie Registered Posts: 115 Dedicated contributor 🦉
    Options
    You need to start with your standard costs. Once you've got those, this is very straightforward, so working out your standard costs should be your first point of call.

    That will leave you with 2kg x £3.50 = £7, 0.5hrs x 10£ = £% and 0.5 x 2 = 1. That gives a total of £13. So your standard marginal cost of production will be £13 x 3200 = 41,600

    Variable overhead rate = 1920 x 2 - 3456 = 384 (favourable)

    Variable overhead efficiency will be (0.5 x 3200 x 2) - (1920 x 2) = -640 (so adverse)

    Hope that helps.
  • sophie_612
    sophie_612 Registered Posts: 136 Dedicated contributor 🦉
    Options

    You need to start with your standard costs. Once you've got those, this is very straightforward, so working out your standard costs should be your first point of call.

    That will leave you with 2kg x £3.50 = £7, 0.5hrs x 10£ = £% and 0.5 x 2 = 1. That gives a total of £13. So your standard marginal cost of production will be £13 x 3200 = 41,600

    Variable overhead rate = 1920 x 2 - 3456 = 384 (favourable)

    Variable overhead efficiency will be (0.5 x 3200 x 2) - (1920 x 2) = -640 (so adverse)

    Hope that helps.

    thanks @CornishPixie when you say start with your standards costs what would i have to do?
  • CornishPixie
    CornishPixie Registered Posts: 115 Dedicated contributor 🦉
    Options
    Ok, so looking at your budgeted quantity columns - these form the basis of the standard costs!

    Materials - 21,000 / 6,000 = £3.50/kg and per unit will be 6,000 / 3,000 = 2kg/unit
    Labour - 15,000 / 1,500 = £10/hour and per unit will be 1,500 / 3,000 = 0.5/unit
    Var o'heads - 3,000 / 1,500 = £2/hour and per unit will be 1,500 / 3,000 = 0.5 OAR

    So, going back to my answer above, to make 1 unit will be (2kg x £3.50) = £7, plus (0.5hour x £10) = £5 plus (0.5 x 2) = £1 giving a total of £13 per unit. multiplied by the actual number of units made gives you £13 x 3200 = £41,600
  • sophie_612
    sophie_612 Registered Posts: 136 Dedicated contributor 🦉
    Options
    @CornishPixie thank you for your help
  • CornishPixie
    CornishPixie Registered Posts: 115 Dedicated contributor 🦉
    Options
    You are welcome.
Privacy Policy