The information given below relates to the forthcoming period for a manufacturer’s operation.
There are four cost centers of which two are involved in production and two are service cost
centers.
…………………………………………………............Production………...........……Service...........
………………………………Total……......Machining……Assembly……Canteen………Stores
………………………………….$……..….......$……....….......$……......……$....….........….$
Allocated costs………..70,022……......…21,328………29,928……….8,437………....10,329
Other costs
Rent and rates………….4,641
Buildings insurance…..3,713
Electricity and gas…….6,800………………………………..Table 1
Plant depreciation…….28,390
Plant insurance………….8,517
…………………………….._______
………………….Total……122,083
…………………………….._______
Area occupied (square metres)..…..........…7,735…………...6,188…….....1,547….......3,094
Plant at cost ($’000)…………………........…1,845………..…..852……....…...—…….…..142
Number of employees……………….........…600………….…..300………......30………….70
Machine hours…………………………........27,200………..….800……….......—……...….—
Direct labor hours…………………….......…6,800……..……18,000……....…—……….....—
Number of stores requisitions……..............27,400…….....….3,400……..….—……….....—
a. Complete the above table 1 by using the most appropriate base.
My answer:
………………………………..Total……..Machining……Assembly……Canteen………Stores
Allocated costs……………70,022………21,328………29,928………8,437………..10,329
Rent and rates…………….4,641………….1934………..1547…………387……………773
Buildings insurance………3,713…………1547………..1238…………309…………….619
Electricity and gas………..6,800…………2833………..2267…………567……………1133
———————————
Plant depreciation……….28,390……….18,450………..8,520……….—…………..1,420
Plant insurance…………….8,517……….5535………….2,556…………—…………….426
……………………………
……………………….Total…….122,083……51,627………46,056………9,700………14,700
Apportion Canteen…………………………..6000…………3000……….(9,700)………..700
Apportion Stores…………………………….13700………..1700………—…………….(15400)
———————————-
……………………….Total……………………..71,327………50,756
My questions: is it correct?
(b). Use this information to calculate a production overhead absorption rate for Machining
department and for Assembly department based on machine hours and labor hours
respectively. Round off to nearest dollars for the above table.
My questions:
How to calculate the production overhead absorption rate?
Thanks a lot for your help.
The information given below relates to the forthcoming period for a manufacturer’s operation.
There are four cost centers of which two are involved in production and two are service cost
centers.
…………………………………………………............Production………...........……Service...........
………………………………Total……......Machining……Assembly……Canteen………Stores
………………………………….$……..….......$……....….......$……......……$....….........….$
Allocated costs………..70,022……......…21,328………29,928……….8,437………....10,329
Other costs
Rent and rates………….4,641
Buildings insurance…..3,713
Electricity and gas…….6,800………………………………..Table 1
Plant depreciation…….28,390
Plant insurance………….8,517
…………………………….._______
………………….Total……122,083
…………………………….._______
Area occupied (square metres)..…..........…7,735…………...6,188…….....1,547….......3,094
Plant at cost ($’000)…………………........…1,845………..…..852……....…...—…….…..142
Number of employees……………….........…600………….…..300………......30………….70
Machine hours…………………………........27,200………..….800……….......—……...….—
Direct labor hours…………………….......…6,800……..……18,000……....…—……….....—
Number of stores requisitions……..............27,400…….....….3,400……..….—……….....—
a. Complete the above table 1 by using the most appropriate base.
My answer:
………………………………..Total……..Machining……Assembly……Canteen………Stores
Allocated costs……………70,022………21,328………29,928………8,437………..10,329
Rent and rates…………….4,641………….1934………..1547…………387……………773
Buildings insurance………3,713…………1547………..1238…………309…………….619
Electricity and gas………..6,800…………2833………..2267…………567……………1133
———————————
Plant depreciation……….28,390……….18,450………..8,520……….—…………..1,420
Plant insurance…………….8,517……….5535………….2,556…………—…………….426
……………………………
……………………….Total…….122,083……51,627………46,056………9,700………14,700
Apportion Canteen…………………………..6000…………3000……….(9,700)………..700
Apportion Stores…………………………….13700………..1700………—…………….(15400)
———————————-
……………………….Total……………………..71,327………50,756
My questions: is it correct?
(b). Use this information to calculate a production overhead absorption rate for Machining
department and for Assembly department based on machine hours and labor hours
respectively. Round off to nearest dollars for the above table.
My questions:
How to calculate the production overhead absorption rate?
Thanks a lot for your help.
0
Comments
-
0
Categories
- All Categories
- 1.2K Books to buy and sell
- 2.3K General discussion
- 12.5K For AAT students
- 331 NEW! Qualifications 2022
- 162 General Qualifications 2022 discussion
- 11 AAT Level 2 Certificate in Accounting
- 57 AAT Level 3 Diploma in Accounting
- 96 AAT Level 4 Diploma in Professional Accounting
- 8.9K For accounting professionals
- 23 coronavirus (Covid-19)
- 273 VAT
- 93 Software
- 275 Tax
- 138 Bookkeeping
- 7.2K General accounting discussion
- 203 AAT member discussion
- 3.8K For everyone
- 38 AAT news and announcements
- 345 Feedback for AAT
- 2.8K Chat and off-topic discussion
- 584 Job postings
- 16 Who can benefit from AAT?
- 36 Where can AAT take me?
- 42 Getting started with AAT
- 26 Finding an AAT training provider
- 48 Distance learning and other ways to study AAT
- 25 Apprenticeships
- 66 AAT membership