AAT level 4 question help
Aliyah97
Registered Posts: 22 New contributor 🐸
please could someone help me work out this question and the workings please


0
Comments
-
Hi Aliyah,
Firstly calculate the number of hours required for production.....32,600 units / 4 units per hour = 8,150 hours required.
Next calculate basic hours available. 2 weeks of 56 staff working 37 hours and 2 weeks of 53 staff working 37 hours.........(112 * 37) + (106 * 37) = 8,066 hours.
The number of overtime hours required is 8,150 - 8,066 = 84 hours.
Hope this helps
AAT Member. Foundation - Distinction 94%Advanced - Distinction 90%Professional - Merit 81%0
Categories
- All Categories
- 1.3K Books to buy and sell
- 2.3K General discussion
- 12.5K For AAT students
- 390 NEW! Qualifications 2022
- 174 General Qualifications 2022 discussion
- 16 AAT Level 2 Certificate in Accounting
- 78 AAT Level 3 Diploma in Accounting
- 114 AAT Level 4 Diploma in Professional Accounting
- 8.9K For accounting professionals
- 23 coronavirus (Covid-19)
- 276 VAT
- 96 Software
- 281 Tax
- 148 Bookkeeping
- 7.2K General accounting discussion
- 211 AAT member discussion
- 3.8K For everyone
- 38 AAT news and announcements
- 345 Feedback for AAT
- 2.8K Chat and off-topic discussion
- 589 Job postings
- 16 Who can benefit from AAT?
- 37 Where can AAT take me?
- 43 Getting started with AAT
- 26 Finding an AAT training provider
- 48 Distance learning and other ways to study AAT
- 24 Apprenticeships
- 67 AAT membership