    Firstly calculate the number of hours required for production.....32,600 units / 4 units per hour = 8,150 hours required.

    Next calculate basic hours available. 2 weeks of 56 staff working 37 hours and 2 weeks of 53 staff working 37 hours.........(112 * 37) + (106 * 37) = 8,066 hours.

    The number of overtime hours required is 8,150 - 8,066 = 84 hours.

    Hope this helps :)