Limiting Factor PLEASE HELP
System
Posts: 100,534 🤖 Admin 🤖
Hope someone can help me solve this:
PRODUCT A:
Selling Price £90
Direct material cost/unit £18
Direct Labour hrs/unit 3
Variable Overheads £29
PRODUCT B:
Selling price £101
Direct material cost/unit £21
Direct labour hrs/unit 3.5
Variable overheads £33
Planned production was units 200 for A and B.
Due to machine breakdown only 80% of planned labour hours will be available.
How to:
Calculate the total labour hours originally planned and the labour hours now available in the month?
Thanks in advance for any help! :P
PRODUCT A:
Selling Price £90
Direct material cost/unit £18
Direct Labour hrs/unit 3
Variable Overheads £29
PRODUCT B:
Selling price £101
Direct material cost/unit £21
Direct labour hrs/unit 3.5
Variable overheads £33
Planned production was units 200 for A and B.
Due to machine breakdown only 80% of planned labour hours will be available.
How to:
Calculate the total labour hours originally planned and the labour hours now available in the month?
Thanks in advance for any help! :P
0
Comments
-
Re:Limiting Factor PLEASE HELP
Seems a bit strange, it looks like a limiting factor question but from your question you don't have to calculate what the new production is?
Originally Planned Labour Hours
200 units * 3hrs = 600hrs
200 units * 3.5hrs = 700hrs
total = 1300hrs (originally planned)
80% of 1300hrs = 1040hrs (now available)
Or was it that the original units to be produced was a combination of products A & B adding up to a total of 200 units and not 200 units of each?
Adrian
0 -
Re:Limiting Factor PLEASE HELP
I was pretty much going to say what Adrian said but got distracted by the golf half way through writing and he nipped in first
If the planned production of A & B adds up to 200, I can't really see that there's any way of answering the question.
I suppose it's a limiting factors question because you're working out the limiting factor. I wouldn't be surprised if the question went on to ask you to work the new production.
Chris
0 -
Re:Limiting Factor PLEASE HELP
Hi, Limiting Factor Analysis is all about getting the most amount of Profit out of a bad situation. Here are some examples. If they don't turn out too well on the post then PM me and I will send you the notes.
Limiting Factor Analysis
PRODUCT
A B C
Selling Price 20 25 30
Variable Cost 15 15 5
Cost Per Unit 5 10 25
Rank 3 2 1
•Rank in the Highest contribution first = in order to maximise profit.
•This decision in only applicable if there are no restrictions on resources
o Materials
Quantities
Money to spend
o Labour
Hours
Money to spend
o Overheads
Hours
Money to spend
•Therefore a decision on producing the production that gives the highest Cost per Unit per Limiting Factor
Example Page 83 of Course Notes
Bill makes
PRODUCT
R S
Selling Price 120 50
Variable Cost 70 25
Cost Per Unit 50 25
Rank 1 2
Limiting Factor – Kilo’s of Material
Limiting Factor = CPU / Limiting Factor
R S
= 50/7 25/2.5
Contribution / Limiting Factor (Kilos of Material) = £7.14 £10.00
RANK 2 RANK 1
Class Example Page 84 Of Course Notes
PRODUCT
A B C
Selling Price 80 20 45
Variable Cost 24 6 15
Other VC 20 8 12
Cost Per Unit 36 6 18
Rank 1 3 2
Labour 24 6 15
Cost/£ of Labour£ 1.50 £1.00 £1.20
New Rank 1 3 2
Optimum Production Plan
Maximum £ for Labour Available £6000
Product A 200 units x 24 (£4800)
£1200
Product C 1200 ÷ CPU 15 = 80 units
0 -
Re:Limiting Factor PLEASE HELP
damn
as I expected the post did not turn out too well, do you want to PM me and I will send you my notes
0 -
Re:Limiting Factor PLEASE HELPlincs wrote:Or was it that the original units to be produced was a combination of products A & B adding up to a total of 200 units and not 200 units of each?
Adrian
Thank you everybody for your replies.
200 is for each product. Yes I think I have to calculate the new production with the limited hours available.
0 -
Re:Limiting Factor PLEASE HELPCJC wrote:I was pretty much going to say what Adrian said but got distracted by the golf half way through writing and he nipped in first

If the planned production of A & B adds up to 200, I can't really see that there's any way of answering the question.
I suppose it's a limiting factors question because you're working out the limiting factor. I wouldn't be surprised if the question went on to ask you to work the new production.
Chris
I'm back again, my head goes around and around this task...
yes, now i have to calculate the contribution per limiting factor per product, but how come?
should I divide for product A for example the available hours:
480 : 200 units= 2.4
or the original hours
600 : 200 = 3
I dont know which one to use for answer that particular question!
0 -
Re:Limiting Factor PLEASE HELP
I've written an example of how to proceed when there are limiting factors which might help - http://www.cjcnet.net/wiki/tiki-index.php?page=limiting+factors
Chris0 -
Re:Limiting Factor PLEASE HELP
CJC I looked at your notes but they don't answer at my particular question. It's the same situation I have seen also in my books while I have a diffent one.
Lets take PRODUCT A:
Selling Price £90
Direct material cost/unit £18
Direct Labour rate £7
Direct Labour hrs/unit 3
Variable Overheads £29
units:200
Original Hours available 600
Limiting Hours available: 480
SOLUTION:
Contribution: 36
Labour: here what to use? 2.4 (480:200) or 3 (600:200)?
Contribution par labour: 15 or 12 (depends which one is used on labour)
In all the exaples I have seen it has been used always the original hours or whatever and then you rank it for determine which product to make. But what's happen when they gave you already the limiting factor before the task?
I'm so confused... :?0 -
Re:Limiting Factor PLEASE HELP
The amount of labour hours needed to make each unit doesn't change just the amount of hours available. The question tells you it takes 3 hours to make Product A - problems with the machines aren't going to change that.
So it's really no different from a standard limiting factor question.
Chris0 -
Re:Limiting Factor PLEASE HELP
Hi, I am really stuck on this assignment and i need your help and advise, im stuck, trying to find the limiting factor, this is really holding me back and I cant seem to move on, any advise? Thanks.
Product A
Selling price: £14000
Material Cost: £9000
Labour Cost: £2800
Demand: 250
Time Taken Days: 0.5
Product B
Selling price: £15500
Material Cost £9800
Labour Cost £3360
Demand: 160
Time Taken Days: 0.6
Product C
Selling price: £16000
Material Cost: £9280
Labour Cost: £3920
Demand: 100
Time Taken Days: 0.7
Product D
Selling price: £15,500
Material Cost: 9,670
Labour Cost: 3,080
Demand: 180
Time Taken Days: 0.55
There are 330 working days and orders for each car: Fixed costs for the year are expected to be £965,400.
Managing Director has told you that the annual profit must be at least £500,000 and cost saving must be made in fixed costs if this minimum figure cannot be otherwise archived.0 -
Re:Limiting Factor PLEASE HELP
Hi guys, i found out what it was, the limiting factor is time.0