Elements Of Costing Practice Assessment 2 Question 8) D) ii) is wrong.

Options
cjkearns
cjkearns Registered Posts: 11
For anyone that has done it I worked out the basic pay and then added the bonus scaled accordingly; as it is a semi-variable cost. The answer wants you to simply scale the labour cost aas a variable cost. It gives two completely different answers and I genuinely don't know what I should be doing now. I have attached the question and answer so you can see what I mean. Any insight would be greatly appreciated. Thanks
Chris.

Comments

  • Denchan
    Denchan Registered Posts: 1
    Options
    hi cris have you managed to find the solution to this particular because I can't seems to work this one either.