Stock reorder level, help.

sunny
sunny Registered Posts: 43 Regular contributor ⭐
Hi,
I got two different formulas of Stock Reorder level, could some smart guy tell me which one is the right one?

1. Reorder level= Maximum usage x Maximum lead time

2. Reorder level= Buffer stock level + (Budgeted usage x Maximum lead time)

Both of them were showed in my textbook, It's too late to send an email to my tutor. Tomorrow is the exam day, Could anyone help me?
:confused1:

Comments

  • Saff
    Saff Registered Posts: 2 New contributor 🐸
    Stock re-order level:

    = Buffer stock + (Max usage x Max lead time)

    Hope this helps.
  • sunny
    sunny Registered Posts: 43 Regular contributor ⭐
    Thank You, dear.:thumbup1:

    But it looks like a different one. One more :laugh: I hope no question of reorder in the exam.
  • sunny
    sunny Registered Posts: 43 Regular contributor ⭐
    HI
    got the answer in the answer paper for DEC 05, Task1.2. They used the formula:
    Reorder level= buffer level+(budegted usage x Maximum lead time)
    Hope it could be helpful to somebody.