ECR Dec 05 Task 2.4

Options
sunny
sunny Registered Posts: 43 Regular contributor ⭐
Hi,
in task 2.4, how can I get the machine hours allocated to Porduct N 300hours rather than 320 hours?
I calculated as below:
the forcast product units for N are 160,000(Task 2.3),
so the machine hours should be: 160,000 x 0.002(machine hours/unit)=320

I dont understand how it be 300 in the answer, could anybody give me a tip? thanks!:thumbup:

Comments

  • Saff
    Saff Registered Posts: 2 New contributor 🐸
    Options
    Think you should just check your answer to task 2.3. I got to be 150,000 forecast sales.
  • sunny
    sunny Registered Posts: 43 Regular contributor ⭐
    Options
    thanks a lot.
    I checked it again, in the topic, there were two forcast figure, first 150000 units in task 2.1, then 160,000 units in task 2.3, which one should we use?:001_rolleyes:
Privacy Policy