Hi,
in task 2.4, how can I get the machine hours allocated to Porduct N 300hours rather than 320 hours?
I calculated as below:
the forcast product units for N are 160,000(Task 2.3),
so the machine hours should be: 160,000 x 0.002(machine hours/unit)=320
I dont understand how it be 300 in the answer, could anybody give me a tip? thanks!:thumbup:
in task 2.4, how can I get the machine hours allocated to Porduct N 300hours rather than 320 hours?
I calculated as below:
the forcast product units for N are 160,000(Task 2.3),
so the machine hours should be: 160,000 x 0.002(machine hours/unit)=320
I dont understand how it be 300 in the answer, could anybody give me a tip? thanks!:thumbup:
0
Comments
-
Think you should just check your answer to task 2.3. I got to be 150,000 forecast sales.0
-
thanks a lot.
I checked it again, in the topic, there were two forcast figure, first 150000 units in task 2.1, then 160,000 units in task 2.3, which one should we use?:001_rolleyes:0
Categories
- All Categories
- 1.2K Books to buy and sell
- 2.3K General discussion
- 12.5K For AAT students
- 322 NEW! Qualifications 2022
- 159 General Qualifications 2022 discussion
- 11 AAT Level 2 Certificate in Accounting
- 56 AAT Level 3 Diploma in Accounting
- 93 AAT Level 4 Diploma in Professional Accounting
- 8.8K For accounting professionals
- 23 coronavirus (Covid-19)
- 273 VAT
- 92 Software
- 274 Tax
- 138 Bookkeeping
- 7.2K General accounting discussion
- 201 AAT member discussion
- 3.8K For everyone
- 38 AAT news and announcements
- 345 Feedback for AAT
- 2.8K Chat and off-topic discussion
- 582 Job postings
- 16 Who can benefit from AAT?
- 36 Where can AAT take me?
- 42 Getting started with AAT
- 26 Finding an AAT training provider
- 48 Distance learning and other ways to study AAT
- 25 Apprenticeships
- 66 AAT membership