Unit 8 Fixed Overheads

sloshed
sloshed Registered Posts: 100 Dedicated contributor 🦉
I am getting very confused on Standard, Budget and Actual when doing fixed overheads...... has anybody any tips :ohmy:

Comments

  • SandyHood
    SandyHood Registered, Moderator Posts: 2,034 mod
    I get the impression that those students working in accountancy practices tend to find standard costing so far from their own experience that it doesn't make sense, whereas even if you work in a small manufacturing business that doesn't use it you can understand how it might fit in.

    I recently tried (with partial success) to explain budget and actual overhead differences by reference to sleeping beauty. Irrespective of whether fairy stories work for you it is important to recognise when each is used.

    Budgeted overheads are our best estimate of the overhead cost before the period starts e.g 20 April for the May accounting period

    Standard overheads absorbed are not known until after the period has finished e.g. 3rd June. It is found by multiplying the ACTUAL number of units produced by the standard hours per unit, a figure which we had set before the period started. This is multiplied by the standard overhead absorption rate per hour another figure which we had set before the period started

    Actual cost is simply the total overhead cost incurred.

    On April 20 I drew up my budget and identified that
    1. fixed overheads for May would be £25,000.
    2. Production for May would be 5,000 units
    3. Labour hours for May would be 10,000 (2 hours per unit)
    This means we have
    a budgeted overhead absorption rate of £25,000/10,000 hrs = £2.50 per hour
    and a standard time per unit of 10,000 hrs/5,000 units = 2 hrs per unit
    Then May happened.
    I then returned to my work on June 3rd and found
    1. Actual fixed overhead was £24,500
    2. Actual production was 4,800 units
    3. Labour hours were 9,900

    So our budgeted overhead was £25,000

    Our standard overhead was 4,800 units x 2hrs per unit x £2.50 per hour = £24,000

    And our actual overhead was £24,500


    This enables us to find the expenditure variance (difference between the budgeted cost and the actual cost) £500 favourable
    And the volume variance (difference between the standard overhead absorbed and the budget) £1,000 adverse

    If you wanted to find out how the volume variance can be attributed to efficiency and to capacity we would have to find the standard overhead absorbed for the actual hours worked (in our case 9,900 hrs x £2.50 per hour)
    £24,750
    So we have an efficiency variance of £750 adverse
    the standard labour time was 4,800 units x 2hrs per unit = 9,600 hrs But we took 9,900 hrs (300 hrs more than the standard) So we were inefficient and 300 hrs x £2.50 = £750 adverse
    And a capacity variance of £250 adverse
    the bugeted hours were 10,000 but we only worked for 9,900 so capacity was 100 less than budget (at £2.50 per hour) £250 adverse
    Sandy
    sandy@sandyhood.com
    www.sandyhood.com
  • 118 11kate
    118 11kate Registered Posts: 115 Dedicated contributor 🦉
    Just jumping in here and being nosey....but that made loads of sense.

    I can work out all the formulas and figures but was finding it hard to explain capacity and efficieny.....yeah I dont know why
    either:blushing:.

    Thats helped loads....."Thank you"

    Kate
Privacy Policy