PEV Exam - what did you think?

12346

Comments

  • Hunnie
    Hunnie Registered Posts: 41 Regular contributor ⭐
    I seem to remember the £414000
    I calculated the additional costs to be:
    Materials 1000 x £60 = £60000
    Labour 1000 x 2 x £14 = £28000
    *It said in the question based on 2 labour hours so I assumed this was how many labour hours were required per unit.
    Therefore my revised gross profit was £326000
    Did anybody else get this or am i completely wrong?

    Fixed overheads should have remained £120000
    Selling & distribution costs and admin costs should also have remained the same as still only 9000 units sold?
  • Guru
    Guru Registered Posts: 33 Regular contributor ⭐
    Hunnie wrote: »
    I seem to remember the £414000
    I calculated the additional costs to be:
    Materials 1000 x £60 = £60000
    Labour 1000 x 2 x £14 = £28000
    *It said in the question based on 2 labour hours so I assumed this was how many labour hours were required per unit.
    Therefore my revised gross profit was £326000
    Did anybody else get this or am i completely wrong?

    Fixed overheads should have remained £120000
    Selling & distribution costs and admin costs should also have remained the same as still only 9000 units sold?


    I *think* you've re-doubled the labour - I thought it was £7 per hour.

    And you're right about sales/dist cost not changing, although the pedant in me can't avoid pointing out that they shouldn't change irrespective of the sales level...
  • pink
    pink Registered Posts: 35 Regular contributor ⭐
    Hunnie wrote: »
    I seem to remember the £414000
    I calculated the additional costs to be:
    Materials 1000 x £60 = £60000
    Labour 1000 x 2 x £14 = £28000
    *It said in the question based on 2 labour hours so I assumed this was how many labour hours were required per unit.
    Therefore my revised gross profit was £326000
    Did anybody else get this or am i completely wrong?

    Fixed overheads should have remained £120000
    Selling & distribution costs and admin costs should also have remained the same as still only 9000 units sold?


    Hi hunnie, I got £28,000 for labour as well, i wish i had left the fixed overheads alone though!!!
  • pink
    pink Registered Posts: 35 Regular contributor ⭐
    im not 100% sure, but I think that the reason I used £14 per labour hour because that is what I calculated in the performance indicators earlier in the question

    Scenario 1 was £14 and scenario 2 £35
  • Hunnie
    Hunnie Registered Posts: 41 Regular contributor ⭐
    Guru wrote: »
    I *think* you've re-doubled the labour - I thought it was £7 per hour.

    And you're right about sales/dist cost not changing, although the pedant in me can't avoid pointing out that they shouldn't change irrespective of the sales level...

    I do remember the £7 rate now you've said that......i'm sure i still multiplied by 2 though *confused*

    I thought that selling and distribution costs would relate to the number of units sold and distributed but then these papers do play with your mind :S
  • pink
    pink Registered Posts: 35 Regular contributor ⭐
    was £7 what they had given us for task 2.3?
  • Hunnie
    Hunnie Registered Posts: 41 Regular contributor ⭐
    Guru wrote: »
    I *think* you've re-doubled the labour - I thought it was £7 per hour.

    And you're right about sales/dist cost not changing, although the pedant in me can't avoid pointing out that they shouldn't change irrespective of the sales level...
    pink wrote: »
    was £7 what they had given us for task 2.3?

    That may be where the £7 came from...my mind is so boggled now that i'm not sure! Speaking of task 2.3 though, i discounted the £30000 running costs by the discount factors but should i have discounted my labour savings also i.e the £105000?
    Another thing i wasn't sure on (as i hadn't looked at discount factors since last year) is should i have started discounting from year 0 i.e. the cost would remain £30000 or should you start discounting from year 1?
  • pink
    pink Registered Posts: 35 Regular contributor ⭐
    I know me too, frustrated I cant remember everything!!

    Looking at the other posts i think in section 1 the labour rate was £7 but then for task 2.1 and 2.2 in the preformance indicators we had to calculate £14.... so thats why used the £14 instead of £7 giving me the £28,000 but who knows, no doubt I am completely worng!!!

    I thought I got a saving of about £108,000 but then the £70,000 that people keep mentioning rings a bell too?! think i probably just did every calculation possible hoping one of them would be right lol!!

    Im sure that i started from year 1 to rather than year 0 ..
  • Hunnie
    Hunnie Registered Posts: 41 Regular contributor ⭐
    pink wrote: »
    I know me too, frustrated I cant remember everything!!

    Looking at the other posts i think in section 1 the labour rate was £7 but then for task 2.1 and 2.2 in the preformance indicators we had to calculate £14.... so thats why used the £14 instead of £7 giving me the £28,000 but who knows, no doubt I am completely worng!!!

    I thought I got a saving of about £108,000 but then the £70,000 that people keep mentioning rings a bell too?! think i probably just did every calculation possible hoping one of them would be right lol!!

    Im sure that i started from year 1 to rather than year 0 ..

    I'm just hoping that i can scrape through on the basis that I provided workings for everything and tried to explain things the best i could! Hopefully they will give me extra marks for setting my answers out neatly haha! On that note, i'm going to bed...need a fresh head to continue PCR revision - fun fun!
  • CJE
    CJE Registered Posts: 9 New contributor 🐸
    Has anyone completed the feedback questionaire on the Students page under lastest news... they use this when marking so it may be a good idea for people to fill this out... they may let us off with the last question ... maybe !?
  • Tracie
    Tracie Registered Posts: 25 Regular contributor ⭐
    pink wrote: »
    Re task 2.2
    I remember that the operating profit given for the first scenario was £414,000
    but I think after calculating all of the adjustments I got my new operating profit to something like £386,700 ish but im not sure.... can anyone remember what they got?
    I got £340,000 and my New Net Assets were £1940,000. Also calculated ROCE as thought that was what they were asking for and got 17.5%

    Did anyone else ge these figures??
  • Jess26182
    Jess26182 Registered Posts: 3 New contributor 🐸
    Thought the exam was a bit easier than June 08 one, still v wordy!! Last question threw me, found out from a friend that it has NOTHING to do with PEV. It is in fact an ECR question from Intermediate - what use is that testing us on a PEV paper, if we haven't done ECR???! AAT were completely unfair there........Had a bash at it, guessed that one....:001_unsure:
  • Polymer xx
    Polymer xx Registered Posts: 13 New contributor 🐸
    hey guys

    can anyone remember whether the hours in section 2 were reduced from 5 to three (i.e. giving a saving of 2 hours) or from 5 to 2 (i.e. giving a saving of three hours). I was under the impression it was the former, but looking at everyones comments here it seems I may have misread the question!!

    cheers!!
  • Ola
    Ola Registered Posts: 4 New contributor 🐸
    ^Joe wrote: »
    Our Tutor did briefly cover it this year :)



    Total= (budgeted Materials / units) x actual units, then use this against the actual cost, IIRC, £3350.
    You need to adjust for the units. Mine did work.

    Aww no!! i got the two split variances right but i must have been having a blonde moment when i did the total cost variance as i just took the two total material figures away from each other to get the variance. NOOOO! well hopefully i did enough in other areas to cover this. :-(
  • Ola
    Ola Registered Posts: 4 New contributor 🐸
    Polymer xx wrote: »
    hey guys

    can anyone remember whether the hours in section 2 were reduced from 5 to three (i.e. giving a saving of 2 hours) or from 5 to 2 (i.e. giving a saving of three hours). I was under the impression it was the former, but looking at everyones comments here it seems I may have misread the question!!

    cheers!!

    It was from 5 to 2 i think with a 3 hour saving
  • nikdan123
    nikdan123 Registered Posts: 11 New contributor 🐸
    I Have totally failed this exam...messed up last question cant remember answering the one about how it affects the p&l. oh well resit in june for me! x
  • Hunnie
    Hunnie Registered Posts: 41 Regular contributor ⭐
    nikdan123 wrote: »
    I Have totally failed this exam...messed up last question cant remember answering the one about how it affects the p&l. oh well resit in june for me! x

    Did anybody get the following?
    Material price variance (glass) £21000A
    Material usage variance £0
    Labour rate variance £0
    Labour efficiency variance £1400F
    FOH expenditure variance £1000A
    FOH efficiency variance £6000F
    OAR £30

    How did you explain the £0 variances?
  • nikdan123
    nikdan123 Registered Posts: 11 New contributor 🐸
    i had nill variance for the material usage but then for some stupid reason i changed it. i think i got the same on others though! whats that OAR?
  • Hunnie
    Hunnie Registered Posts: 41 Regular contributor ⭐
    nikdan123 wrote: »
    i had nill variance for the material usage but then for some stupid reason i changed it. i think i got the same on others though! whats that OAR?

    Overhead absorption rate = budgeted overheads / budgeted labour hours£120000 / 4000 = £30
  • nikdan123
    nikdan123 Registered Posts: 11 New contributor 🐸
    i didnt know it asked for that either. oh man! never mind am not that bothered ha nothing i can do about it now
  • Suzie1982
    Suzie1982 Registered Posts: 4 New contributor 🐸
    I got completely thrown on variances - the zero ones confused me but ratios were ok thought there was more writing though for this one

    had a go at section 2 didnt d anything on depreciation - will prob have to take again.
  • Guru
    Guru Registered Posts: 33 Regular contributor ⭐
    Hunnie wrote: »

    How did you explain the £0 variances?

    Well, it shows that the budget was accurate, ie that wages really were £7 per hour, and materials really were 5Kg/unit (or whatever).
  • confused!!
    confused!! Registered Posts: 130 Dedicated contributor 🦉
    Tracie wrote: »
    I got £340,000 and my New Net Assets were £1940,000. Also calculated ROCE as thought that was what they were asking for and got 17.5%

    Did anyone else ge these figures??

    I got £312,700, but i used £14 to work out the labour and also adjusted the overheads (wrong i know!)
  • lork
    lork Registered Posts: 97 Regular contributor ⭐
    Guru wrote: »
    I see lots of people upset about this, but shouldn't we be able to deal with the material we've previously learned? Would we have any justification in complaining if we were asked to complete a VAt return? I understand the surprise, I just don't think we're entitled to complain - we're only a few months away from a professional qualification....

    Whilst I completely agree that we should be able to deal with previous material, surely this is the whole point of doing 'modular' exams, ie, learn a subject, sit an exam. I'm sure if students expected to be tested on absolutely anything learned over the past three years, we would all revise everything we've ever learned, rather than concentrate solely on the current unit. I still think it was unfair to throw it in at the end but I believe the same thing happened in June with gearing and interest cover ratios.
  • lork
    lork Registered Posts: 97 Regular contributor ⭐
    pink wrote: »
    im not 100% sure, but I think that the reason I used £14 per labour hour because that is what I calculated in the performance indicators earlier in the question

    Scenario 1 was £14 and scenario 2 £35

    Wasn't that £14 and £35 per unit, not per hour in the performance indicators?
  • NBB
    NBB Registered Posts: 125 Dedicated contributor 🦉
    lork wrote: »
    Wasn't that £14 and £35 per unit, not per hour in the performance indicators?


    Yes Lork, It was per unit not per hour.
  • King of the Mountains
    King of the Mountains Registered Posts: 66 Regular contributor ⭐
    lork wrote: »
    Whilst I completely agree that we should be able to deal with previous material, surely this is the whole point of doing 'modular' exams, ie, learn a subject, sit an exam. I'm sure if students expected to be tested on absolutely anything learned over the past three years, we would all revise everything we've ever learned, rather than concentrate solely on the current unit. I still think it was unfair to throw it in at the end but I believe the same thing happened in June with gearing and interest cover ratios.

    I completely agree, however GURU I complete VAT Returns on a regular basis and have done for the past 10 years but unfortunately I don't do discounted lifecycle costing. Now I've had time to think about the question it is a relativley simple calculation that we are probably all more than capable of.
  • belleire
    belleire Registered Posts: 5 New contributor 🐸
    PEV has left me deflated!

    Hi,

    I studied so hard for PEV as it's my final exam thought I would be skipping out of the exam yesterday but NO the last question 2.3 left me feeling very unsure as to whether I could have passed or not!

    Can someone please put me out of my misery I multiplied the maintenance costs by each year of the figures given 0.9 and the rest can't remember what they were to give me a lower figure than I started with added all them together with the cost of the machinery and minused the sale proceeds amount?

    Basically can some one answer whether the discounted amount is added or taken away from the total? Does it make the value greater or less? Confused.com:huh:
  • tauq786x
    tauq786x Registered Posts: 35 Regular contributor ⭐
    I think that if most people eff'd up on 2.3 then they unlikely to make us fail coz of it

    Section 1 was easy... but i made alot of silly mistakes on Section 2 and with 2.3 being messed looks like im gonna resit in june!
  • iainiow
    iainiow Registered Posts: 20 New contributor 🐸
    how do people remember exact figures from the exam yesterday :laugh: i can remember walking in, doing the paper and walking out - 24 hours later i remember nothing of what i wrote down lol!!!!!!!!!!:thumbup:
Privacy Policy