Pev question
NAJC
Registered Posts: 44 Regular contributor ⭐
I have been given this question and have absolutly no idea where to start ?.
Any help is much appreciated.
the standard cost for one widget is
Quantity Unit Total
Direct materials 3kg £6 £18
direct labour 0.5 hrs £8 £4
fixed overheads 0.5 hrs £50 £25
_______
£47
budgeted monthly production is 8000 widgets
actual production is 10000 widgets
28500 kgs material were purchased for £176700
5300 hrs were worked at a cost of £8.10 per hr
overheads were absorbed on a direct labour hour basis
actual fixed production overheads were £212000
calculate :
the budgeted production overheads
the actual price of material per kg
standard cost of actual production using absorbtion costing
standard cost of actual production using marginal costing
the materials price and usage variances
the labour rate and efficiency variances
the fixed overhead expenditure, capacity, volume and efficiency variance
then reconcile the standard absorbtion cost of actual production with the actual cost
reconcile the standard marginal cost
AHH HELP PLEASE !
Any help is much appreciated.
the standard cost for one widget is
Quantity Unit Total
Direct materials 3kg £6 £18
direct labour 0.5 hrs £8 £4
fixed overheads 0.5 hrs £50 £25
_______
£47
budgeted monthly production is 8000 widgets
actual production is 10000 widgets
28500 kgs material were purchased for £176700
5300 hrs were worked at a cost of £8.10 per hr
overheads were absorbed on a direct labour hour basis
actual fixed production overheads were £212000
calculate :
the budgeted production overheads
the actual price of material per kg
standard cost of actual production using absorbtion costing
standard cost of actual production using marginal costing
the materials price and usage variances
the labour rate and efficiency variances
the fixed overhead expenditure, capacity, volume and efficiency variance
then reconcile the standard absorbtion cost of actual production with the actual cost
reconcile the standard marginal cost
AHH HELP PLEASE !
0
Comments
-
Re: Pev
Hello
Just to find out, have you done Pev in the past? if so do you know the difference between absorption costing and marginal costing? it is good to know the differences before going through with the question given.
Just a quick clue,
Budgeted monthly production is 8000 widget * £6.00 = 48000
Actual Material price cost is £176700/28500 = £6.20
Therefore the budgeted material cost is =£6.00
Hope this help0 -
the budgeted production overheads
the standard cost for one widget is
fixed overheads 0.5 hrs £50 per hour
Budgeted production 8000 widgets
so budgeted hours 8000 widgets x 0.5 hrs per widget = 4,000 hours
4,000 hours @ £50 per hour = £200,000Sandy
sandy@sandyhood.com
www.sandyhood.com0 -
standard cost of actual production using absorption costing
standard cost of actual production using absorption costing
standard absorbtion cost of actual production
standard cost of one widget £47
x units produced 10,000
standard cost of actual production using absorption costing = £470,000Sandy
sandy@sandyhood.com
www.sandyhood.com0 -
standard cost of actual production using marginal costing
standard cost of actual production using marginal costing
standard marginal cost of actual production
standard marginal cost of one widget £22
x units produced 10,000
standard cost of actual production using absorption costing = £220,000Sandy
sandy@sandyhood.com
www.sandyhood.com0 -
I have been given this question and have absolutly no idea where to start ?.
Any help is much appreciated.
the standard cost for one widget is
//////////////////..............Quantity..............Unit..........Total
Direct materials.................3kg...................£6............£18
direct labour.....................0.5 hrs..............£8.............£4
fixed overheads.................0.5 hrs.............£50............£25
_______
.............................................................................£47budgeted monthly production is 8000 widgets actual production is 10000 widgets 28500 kgs material were purchased for £176700 5300 hrs were worked at a cost of £8.10 per hr overheads were absorbed on a direct labour hour basis actual fixed production overheads were £212000 calculate : [highlight]1 the budgeted production overheads[/highlight] Each unit will absorb £25 in overheads Therefore budgeted production = 8000 units x £25 = £200,000 [highlight]2 the actual price of material per kg[/highlight] Actual material price paid divide by actual material weight £176,700 / 28,500kg = £6.20 per kg [highlight]3 standard cost of actual production using absorption costing[/highlight] standard cost per unit is £47 Actual production is 10,000 units Therefore 10,000 x £47 = £470,000 [highlight]4 standard cost of actual production using marginal costing[/highlight] standard marginal cost = (18+4) = £22 std cost of Actual Marginal costing = 10,000 units x £22 = £220,000 [highlight]5 the materials price and usage variances[/highlight] Price Variance budgeted price =£6 Actual price paid = £6.20 – more then budgeted therefore ADVERSE (£6.20 - £6.00) x 28,500 = £5700 Adverse Usage Variance Budgeted usage 3 kg (3 x 10,000 = 30,000 kg) Actual Usage = 28,500 kg Less then budgeted therefore FAVOURABLE (30,000 kg – 28,500kg) x £6 = £9,000 Favourable [b]Double Check Flex Material budget at 10,000 units (10,000 x £18)=£180,000 expected to pay £180,000 less £176,700 = £3,300 FAVOURABLE (paid less then expected) Price Variance plus Usage variance = Total Variance £5,700 (A) + £9,000 (F) = £3,300 FAVOURABLE = AGREED! [/b] [highlight]6 the labour rate and efficiency variances[/highlight] Labour Rate Variance Expected to pay per hr £8.00 Actual paid per hr £8.10 more then expected therefore ADVERSE (£8.10 – £8.00) X 5300 HRS = £530 ADVERSE Efficiency Variance Expected to use hrs to produce 10,000 units = 10,000 x 0.50 = 5000 hrs Actual hrs used to produce 10,000 units = 5300 hrs- more then expected ADVERSE variance (5300-5000) x £8.00 = £2,400 ADVERSE [b]Double Check Flex Labour budget at 10,000 units (10,000 x £4)=£40,000 expected to pay £40,000 less (5300 Hrs X £8.10= £42930= £2,930 ADVERSE (paid more then expected) Rate Variance Efficiency variance = Total Variance £530 (A) + £2,400 (A) = £2,830 ADVERSE = AGREED! [/b] [highlight]7 the fixed overhead expenditure, capacity, volume and efficiency variance[/highlight] Fixed Overhead Expenditure Variance Budgeted O heads less Actual O heads £200,000 – £212,000 = £12,000 ADVERSE FO Volume (Production) Variance Budgeted Hrs = 8000units * 0.5 hr = 4000 hrs Expected Hrs = 10,000 units * 0.5Hrs = 5000 hrs (5000 – 4000) x £50 = £50,000 FAVOURABLE (more then budgeted) FO Capacity Variance Budgeted Hrs = 8000 units * 0.5 hr = 4000 hrs Actual Hrs used to Absorb overheads = 5300 hrs (5300 – 4000) x£50 = £65,000 FAVOURABLE FO efficiency variance Expected Hrs = 10,000 units * 0.5Hrs = 5000 hrs Actual Hrs used to Absorb overheads = 5300 hrs (5300 -5000) X£50 = £15,000 ADVERSE [b][highlight]Double Check Capacity variance plus Efficiency variance = Volume (production) Variance £65,000 (F) + £15,000 (A) = £50,000 (F) = Agreed[/highlight] Double Check Flex Fixed Overheads budget at 10,000 units (10,000 x £25)=£250,000 expected to absorb Overheads Actual Fixed Overheads = £212,000 Total Fixed Overhead Variance = £250,000 - £212,000 = £38,000 FAVOURABLE Expenditure Variance less Volume (production) variance = Total Fixed Overhead Variance £12,000(A) + £50,000 (F) = £38,000 = Agreed![/b] [highlight]8 [b]reconcile the standard absorption cost of actual production with the actual cost [/b][/highlight] £ £ £ Standard Cost of 10,000 units 470,000 Material Price Variance 5,700 (A) Material Usage Variance 9,000 (F) Labour Rate Variance 530 (A) Labour Efficiency Variance 2,400 (A) Fixed Overheads Expenditure variance 12,000 (A) FO Volume (production) variance 50,000(F) Total Variances 59,000(F) 20,630 (A) 38,370 (F) Actual Production Cost 431,630 Material 176,700 Labour (5300 x 8.10) 42,930 Overheads 212,000 431,630 [highlight]9 [b]reconcile the Standard Marginal cost of actual production with the actual cost [/b][/highlight] £ £ £ Std Marginal Cost of 10,000 units 220,000 Material Price Variance 5,700 (A) Material Usage Variance 9,000 (F) Labour Rate Variance 530 (A) Labour Efficiency Variance 2,400 (A) Total Variances 9,000(F) 8,630 (A) 370 (F) Actual Production Cost 219,630 Material 176,700 Labour (5300 x 8.10) 42,930 219,630
0
Categories
- All Categories
- 1.2K Books to buy and sell
- 2.3K General discussion
- 12.5K For AAT students
- 323 NEW! Qualifications 2022
- 160 General Qualifications 2022 discussion
- 11 AAT Level 2 Certificate in Accounting
- 56 AAT Level 3 Diploma in Accounting
- 93 AAT Level 4 Diploma in Professional Accounting
- 8.8K For accounting professionals
- 23 coronavirus (Covid-19)
- 273 VAT
- 92 Software
- 274 Tax
- 138 Bookkeeping
- 7.2K General accounting discussion
- 201 AAT member discussion
- 3.8K For everyone
- 38 AAT news and announcements
- 345 Feedback for AAT
- 2.8K Chat and off-topic discussion
- 582 Job postings
- 16 Who can benefit from AAT?
- 36 Where can AAT take me?
- 42 Getting started with AAT
- 26 Finding an AAT training provider
- 48 Distance learning and other ways to study AAT
- 25 Apprenticeships
- 66 AAT membership