Financial Performance Help

Sammmy88
Sammmy88 Registered Posts: 283 Dedicated contributor 🦉
I need urgent help!!

I have my re-take tomorrow, and the one thing i failed miserably on is on CBT 2: Tasks 1.2 and 1.3..

Please can someone help?

Thank you
Level 2 - Passed 2011
Level 3 - Passed 2012
Level 4 - Passed 2014

Awaiting to start CIMA :)

Comments

  • Morpheus1980
    Morpheus1980 Registered Posts: 120 Beyond epic contributor 🧙‍♂️
    Hi Sammy, let's see if I can help on CBT 2 1.2 first of all:

    Direct material usage

    Take the actual amount of materials used (1,000) and price it at the standard rate (£9,000 / 1,000 litres = £9). This makes £9,000

    Then, flex the budget to arrive at how much material we should have used. So, divide 1,000 litres by 200,000 then multiply by 190,000 (actual units) to arrive at 950 litres, and multiply by £9 (standard cost per litre). This makes £8,550

    As the actual cost of material used was £450 more than budgeted, this makes it adverse

    Direct material price

    Actual price for actual material purchased is £8,500
    Actual materials purchased (1,000 litres) x standard cost (£9) is £9,000

    As the price we paid for materials is £500 less than budgeted, this is favourable

    Direct labour rate
    Actual price for actual labour is £5,760
    Actual labour hours (360) at the standard rate (£15...flex the budget for this, so £6,000 / 400 hours) is £5,400

    As the rate we paid for labour is £360 more than budget, this is adverse

    Direct labour efficiency

    Actual labour hours at standard rate (calculated above) is £5,400
    Hours we should have incurred for labour (again, flex the budget so £6,000 / 200,000 units x 190,000 units) is £5,700

    As the amount we paid for actual labour is £300 less than budgeted, this is favourable

    Does that make any sense? I find that you have to keep practicing variances over and over again to get them.

    I'll now have a look at task 1.3 for you.
  • Morpheus1980
    Morpheus1980 Registered Posts: 120 Beyond epic contributor 🧙‍♂️
    Task 1.3:

    Fixed overhead capacity

    First, we are told that production overheads are absorbed on a labour hour basis, so we use labour hours here (4,250)

    Multiply 4,250 by the standard cost of fixed overheads (£104,125 / 4,250 hours = £24.50) = £104,125

    Actual hours at standard cost is 4,200 hours x £24.50 = £102,900

    As the actual overheads are £1,225 under the budgeted capacity, they are adverse

    Fixed overhead expenditure
    Budgeted overheads are £104,125
    Actual overheads are £98,450

    As our actual overheads are less than budgeted, the £5,675 difference is favourable

    Fixed overhead efficiency
    Actual hours at the standard rate is 4,200 hours x £24.50 = £102,900

    Actual hours that should have been used for production - flex the budget. 4,250 hours / 17,000 units x 18,000 units = 4,500 hours. Multiply by the standard rate of £24,50 = £110,250

    As the hours we used for production are less than budgeted, the £7,350 is favourable
  • Morpheus1980
    Morpheus1980 Registered Posts: 120 Beyond epic contributor 🧙‍♂️
    Oh, and Sammy, if this all appears like double Dutch, check out the Fixed Overhead Variances worksheet, which is available under My AAT > E-learning resources and Green Light Tests > Level 4 Diploma > Financial Performance, because this explains all of the fixed overhead variances.

    Don't panic, and good luck for tomorrow :)
  • Sammmy88
    Sammmy88 Registered Posts: 283 Dedicated contributor 🦉
    Thank you so so much! Makes so much more sense!! :-)
    Level 2 - Passed 2011
    Level 3 - Passed 2012
    Level 4 - Passed 2014

    Awaiting to start CIMA :)
  • omega man
    omega man Registered Posts: 283
    Morpheus-check your work
    I think the last answer is £7350 favourable
  • Morpheus1980
    Morpheus1980 Registered Posts: 120 Beyond epic contributor 🧙‍♂️
    Oops! Transposition error. I did my workings though, so should still get 1 mark *wink*
Privacy Policy