Financial Performance - Overheads absorption.

Options
JohnPj
JohnPj Registered Posts: 38 Regular contributor ⭐
Hey guys, I'm rather confused about absorbing fixed costs. I know to get the OAR we divide the BUDGETED O/H/ basis on which its absorbed,usually hours.
However to know if we have over or under absorbed ? Do we get the standard for actual fixed costs - actual overheads ????

Also I got this question which totally through me off...

During december there was OVER absorption of fixed overheads of 25,000£. Actual fixed o/h in Dec was 551,000.. What was actual fixed overheads in December ? ...

:( HELP!! have my exam soon and I fear of failing this one

Comments

  • PeterC
    PeterC Registered, Tutor Posts: 245 Dedicated contributor 🦉
    Options
    If your OAR is based on labour hours, then the overhead absorbed is OAR X ACTUAL HOURS.
    Compare this with the ACTUAL OVERHEAD

    eg.
    OAR = £10/labour hour
    Hours worked last month = 400
    Actual overhead last month = ££3,900

    Over-absorption = (10 x 400) - 3,900 = £100

    I don't think the question you quote should be exactly as you have presented it.

    Perhaps is should be:
    During december there was OVER absorption of fixed overheads of 25,000£. Fixed o/h absorbed in Dec was 551,000.. What was actual fixed overheads in December ?

    The answer would then be
    Actual overhead = Overhead absorbed - over absorption = 551,000 - 25,000 = 526,000
  • JohnPj
    JohnPj Registered Posts: 38 Regular contributor ⭐
    Options
    Thank you for that ! However the exam Question is like that and the answer we add the over to the actual December :;
  • SandyHood
    SandyHood Registered, Moderator Posts: 2,034 mod
    Options
    JohnPj

    The question you wrote is
    During december there was OVER absorption of fixed overheads of 25,000£. Actual fixed o/h in Dec was 551,000.. What was actual fixed overheads in December ? ...

    As you can see it says the Actual fixed o/h in Dec was 551,000 and What was actual fixed overheads in December ?

    I'm going to make a guess that you meant to write:
    During december there was OVER absorption of fixed overheads of 25,000£. Actual fixed o/h in Dec was 551,000.. What was absorbed fixed overheads in December ? ...


    If that is what you intended to write, you know that the overheads incurred were lower than the overhead absorbed and the difference was £25,000.
    On that basis the overhead absorbed would be £551,000 + £25,000 = £576,000

    Does that agree with what you were looking for?

    Sandy
    www.sandyhood.com
    sandy@sandyhood.com
    Sandy
    sandy@sandyhood.com
    www.sandyhood.com
  • JohnPj
    JohnPj Registered Posts: 38 Regular contributor ⭐
    Options
    Thanks sandy ! I was gettin confused as I was thinkin if budgeted was lower than actual , that was an over absorption. But it's if budgeted is more than actual then it's an over asborption ( correct me I'm I'm wrong )
  • SandyHood
    SandyHood Registered, Moderator Posts: 2,034 mod
    edited April 2016
    Options
    John
    I must correct you.
    If we have over absorbed overhead it is because the labour hours worked x the overhead absorption rate is more than the actual cost.
    Please only use budgeted overhead cost and budgeted labour hours to set the OAR. Once that has been done, don't go back to those budgeted totals.
    This is an area other people find tricky. You are not alone.
    But stick to this
    Overhead absorbed
    less overhead cost incurred
    = over/(under) absorbed overhead

    And overhead absorbed is (using my garage example) mechanics' hours x overhead absorption rate per hour.

    There are two causes of over/(under) absorption, but you must master this aspect before you consider them
    Sandy

    Here is a link to another post I have made recently on this topic. This is based on a garage (hence my reference to garages above).
    http://forums.aat.org.uk/discussion/comment/447319/#Comment_447319
    Sandy
    sandy@sandyhood.com
    www.sandyhood.com
  • SandyHood
    SandyHood Registered, Moderator Posts: 2,034 mod
    edited April 2016
    Options
    The two causes of overheads being over or under asbsorbed
      1. The Actual Overhead cost is much higher (or lower) than Budgeted
        In standard costing this is called the Fixed Overhead Expenditure Variance
      2. The standard hours produced (units produced x standard time per unit) are more or less than the budgeted hours
        In standard costing this is called the Fixed Overhead Volume Variance

    Sandy
    sandy@sandyhood.com
    www.sandyhood.com
Privacy Policy