Financial Performance - Overheads absorption.
JohnPj
Registered Posts: 38 Regular contributor ⭐
Hey guys, I'm rather confused about absorbing fixed costs. I know to get the OAR we divide the BUDGETED O/H/ basis on which its absorbed,usually hours.
However to know if we have over or under absorbed ? Do we get the standard for actual fixed costs - actual overheads ????
Also I got this question which totally through me off...
During december there was OVER absorption of fixed overheads of 25,000£. Actual fixed o/h in Dec was 551,000.. What was actual fixed overheads in December ? ...
HELP!! have my exam soon and I fear of failing this one
However to know if we have over or under absorbed ? Do we get the standard for actual fixed costs - actual overheads ????
Also I got this question which totally through me off...
During december there was OVER absorption of fixed overheads of 25,000£. Actual fixed o/h in Dec was 551,000.. What was actual fixed overheads in December ? ...
HELP!! have my exam soon and I fear of failing this one
0
Comments
-
If your OAR is based on labour hours, then the overhead absorbed is OAR X ACTUAL HOURS.
Compare this with the ACTUAL OVERHEAD
eg.
OAR = £10/labour hour
Hours worked last month = 400
Actual overhead last month = ££3,900
Over-absorption = (10 x 400) - 3,900 = £100
I don't think the question you quote should be exactly as you have presented it.
Perhaps is should be:
During december there was OVER absorption of fixed overheads of 25,000£. Fixed o/h absorbed in Dec was 551,000.. What was actual fixed overheads in December ?
The answer would then be
Actual overhead = Overhead absorbed - over absorption = 551,000 - 25,000 = 526,0000 -
Thank you for that ! However the exam Question is like that and the answer we add the over to the actual December :;0
-
JohnPj
The question you wrote is
During december there was OVER absorption of fixed overheads of 25,000£. Actual fixed o/h in Dec was 551,000.. What was actual fixed overheads in December ? ...
As you can see it says the Actual fixed o/h in Dec was 551,000 and What was actual fixed overheads in December ?
I'm going to make a guess that you meant to write:
During december there was OVER absorption of fixed overheads of 25,000£. Actual fixed o/h in Dec was 551,000.. What was absorbed fixed overheads in December ? ...
If that is what you intended to write, you know that the overheads incurred were lower than the overhead absorbed and the difference was £25,000.
On that basis the overhead absorbed would be £551,000 + £25,000 = £576,000
Does that agree with what you were looking for?
Sandy
www.sandyhood.com
sandy@sandyhood.comSandy
sandy@sandyhood.com
www.sandyhood.com0 -
Thanks sandy ! I was gettin confused as I was thinkin if budgeted was lower than actual , that was an over absorption. But it's if budgeted is more than actual then it's an over asborption ( correct me I'm I'm wrong )0
-
John
I must correct you.
If we have over absorbed overhead it is because the labour hours worked x the overhead absorption rate is more than the actual cost.
Please only use budgeted overhead cost and budgeted labour hours to set the OAR. Once that has been done, don't go back to those budgeted totals.
This is an area other people find tricky. You are not alone.
But stick to this
Overhead absorbed
less overhead cost incurred
= over/(under) absorbed overhead
And overhead absorbed is (using my garage example) mechanics' hours x overhead absorption rate per hour.
There are two causes of over/(under) absorption, but you must master this aspect before you consider them
Sandy
Here is a link to another post I have made recently on this topic. This is based on a garage (hence my reference to garages above).
http://forums.aat.org.uk/discussion/comment/447319/#Comment_447319Sandy
sandy@sandyhood.com
www.sandyhood.com0 -
The two causes of overheads being over or under asbsorbed
- The Actual Overhead cost is much higher (or lower) than Budgeted
In standard costing this is called the Fixed Overhead Expenditure Variance - The standard hours produced (units produced x standard time per unit) are more or less than the budgeted hours
In standard costing this is called the Fixed Overhead Volume Variance
Sandy
sandy@sandyhood.com
www.sandyhood.com0 - The Actual Overhead cost is much higher (or lower) than Budgeted
Categories
- All Categories
- 1.2K Books to buy and sell
- 2.3K General discussion
- 12.5K For AAT students
- 322 NEW! Qualifications 2022
- 159 General Qualifications 2022 discussion
- 11 AAT Level 2 Certificate in Accounting
- 56 AAT Level 3 Diploma in Accounting
- 93 AAT Level 4 Diploma in Professional Accounting
- 8.8K For accounting professionals
- 23 coronavirus (Covid-19)
- 273 VAT
- 92 Software
- 274 Tax
- 138 Bookkeeping
- 7.2K General accounting discussion
- 201 AAT member discussion
- 3.8K For everyone
- 38 AAT news and announcements
- 345 Feedback for AAT
- 2.8K Chat and off-topic discussion
- 582 Job postings
- 16 Who can benefit from AAT?
- 36 Where can AAT take me?
- 42 Getting started with AAT
- 26 Finding an AAT training provider
- 48 Distance learning and other ways to study AAT
- 25 Apprenticeships
- 66 AAT membership